Domain | Regulatory | IBC | ESI Act | Pre-CIRP Statutory Dues
The Position
K...
By J the App
The Madras High Court has held that recovery of ESI contribution and consequential interest relating to the period before commencement of CIRP is unsustainable after approval of the resolution plan. Applying Section 53 of the IBC and the Supreme Court's ruling in Ghanashyam Mishra, the Court declined to permit recovery of pre-CIRP dues. Damages and interest attributable to the post-CIRP period, however, were left recoverable after separate quantification by the ESI authorities.
Domain | Regulatory | IBC | ESI Act | Pre-CIRP Statutory Dues
The Position
K...
Read the full article in the app