RKD Constructions paid advances to San Commodities LLP against purchase orders for the supply of TMT bars. While part of the material was supplied, the balance remained undelivered and the unadjusted advance was not refunded. The corporate debtor issued two cheques aggregating ₹3.85 crore towards repayment, but both were dishonoured. NCLT held that an advance paid for the supply of goods, which remains unrefunded when the supply is not completed, qualifies as operational debt under Section 5(21) of the IBC. It further held that the dishonoured repayment cheques and consequent Section 138 proceedings did not constitute a pre-existing dispute. The Section 9 application was admitted and CIRP commenced.